中巴经济走廊作为“一带一路”倡议的六大走廊之一,通过两国多方面的合作,促进了巴基斯坦的经济和社会发展,同时进一步密切了中巴全天候战略合作伙伴关系,为巴基斯坦的发展提供了重要机遇。中国能建葛洲坝集团股份有限公司(葛洲坝集团)巴基斯坦联合能源JHIMPIR(99WM)风电一期项目是中巴经济走廊优先实施项目,该项目位于巴基斯坦信德省JHIMPIR区域,巴基斯坦南部重镇卡拉奇市东北,距离卡拉奇市约110km,距卡西姆港约120km,风资源丰富。
The China-Pakistan Economic Corridor (CPEC), one of the six major corridors under the BRI, has played a significant role in promoting economic and social development in Pakistan through multifaceted cooperation between the two countries. It has further strengthened the all-weather strategic partnership between China and Pakistan, providing crucial opportunities for Pakistan's development. The China Gezhouba Group Co., Ltd. (CGGC) and United Energy Pakistan (UEP) JHIMPIR (99 WM) Wind Power Phase I Project is a priority implementation project of CPEC. Located in JHIMPIR region of Sindh Province, northeast to Karachi, the hub of southern Pakistan, about 110 km from Karachi, and about 120 km from Port Qasim, the project benefits from abundant wind resources.
该项目由葛洲坝集团作为EPC总承包,提供“融资、设计、采购、安装、调试、运维”一站式解决方案。该项目所在地属于高温沙漠地区,干燥、干旱、高温、高温差等恶劣环境,为风机基础等大体积混凝土的施工带来极大的挑战,项目团队重视、鼓励技术创新,技术专家带头攻坚克难,并形成了“风机环网通讯技术”、“大体积混凝土施工技术”、“智能化无功补偿系统”等一大批科技成果。项目的顺利实施,为中国技术、中国标准、中国设备走向世界做出了新的贡献。项目部重视属地化管理,累计聘用属地员工1,018人次,高峰期聘用属地员工人数达500余名,占项目员工总数70%以上,同时组织技术培训,有效缓解了当地的就业压力、提高了当地工人操作水平;项目还建立了属地化人才认证体系,对属地化员工进行分层次动态管理,从源头上提高人才库中巴基斯坦属地员工聘用和管理的效率,便于人才推荐和培训提升,为当地可持续发展做出了突出贡献
CGGC serves as the Engineering, Procurement, and Construction (EPC) contractor for the project, providing a comprehensive "financing, design, procurement, installation, commissioning, and operation" solution. The project situated in a high-temperature desert region, presents challenging conditions such as dryness, aridity, high temperatures, and significant temperature variations, which pose a great challenge for the construction of large-volume concrete structures like wind turbine foundations. The project team places a strong emphasis on and encourages technological innovation. Technical experts take the lead in overcoming difficulties, resulting in a multitude of technological achievements such as "Cyclic Structure Wind Turbine Communication Technology", "Large Volume Concrete Construction Technology", and "Intelligent Reactive Power Compensation System". The successful implementation of the project has made a new contribution to the global dissemination of Chinese technology, standards, and equipment. The project prioritizes localized management, employing a total of 1,018 local staff, with over 500 local employees during peak periods, accounting for over 70% of the total project workforce. The project also provides technical training, effectively alleviating local employment pressures and enhancing the operational skills of local workers. Additionally, the project has established a localized talent certification system, dynamically managing local employees at different levels, enhancing the efficiency of recruiting and managing local Pakistani staff, facilitating talent recommendation, training, and advancement and making a significant contribution to local sustainable development.
巴基斯坦风电项目全景图
Panoramic View of Pakistan Wind Power Project
项目于2017年7月31日正式通过验收,转入商业运营阶段,每年可为巴基斯坦电网提供2.6亿千瓦时的绿色能源,有效的缓解了巴基斯坦的电力紧缺问题,同时避免了传统能源带来的高碳排放,助力当地的经济发展的同时,践行联合国全球可持续发展项目标。
The project officially passed acceptance on July 31, 2017, entering the commercial operational phase. It contributes 260 million kilowatt-hours of green energy annually to the Pakistan power grid, effectively alleviating the country's power shortage. Simultaneously, it mitigates the high carbon emissions associated with traditional energy, supporting local economic development and aligning with the United Nations' Global Sustainable Development Goals.